SemiMedia SemiMedia
  • Breaking News
  • MarketWatch
  • Distribution
  • Manufacturer
  • Video
  • About us
Home › MarketWatch › Semiconductor equipment lead time extended to 18 to 30 weeks
  • 0

Semiconductor equipment lead time extended to 18 to 30 weeks

SemiMediaEdit
June 23, 2022

According to reports, the lead time of semiconductor production equipment has been extended to 18 to 30 months, and the overall expansion plans of wafer foundries such as TSMC, UMC, PSMC, VIS, SMIC, and GlobalFoundries will be forced to extend by about 2 to 9 months. It is expected that the year-on-year growth rate of wafer production capacity will drop to 8% in 2023.

The report pointed out that before the outbreak of Covid-19, the lead time of semiconductor production equipment was about 3 to 6 months. Since 2020, the border control implemented by various countries due to the epidemic has led to logistics blockage, and strong demand has driven the production expansion of semiconductor manufacturers. For these reasons, the lead time has been extended again to 12 to 18 months.

In 2022, affected by the conflict between Russia and Ukraine, logistics blockage, and insufficient semiconductor chip production capacity, the shortage of raw materials and chips affected the production of semiconductor equipment.

Except for EUV lithography equipment with a fixed annual output, the lead time of other equipment has been extended to 18 to 30 months. Among them, DUV lithography equipment is the most affected, followed by CVD/PVD deposition and etching equipment.

The report further pointed out that at present, semiconductor manufacturers mainly rely on production adjustment and resource reallocation to support capacity utilization. The expansion of wafer foundries is delayed by factors such as equipment delivery delays and plant construction delays, which will cause the year-on-year growth rate of global wafer foundry capacity to drop to 8% in 2023.

Related

electronic components news Semiconductor equipment lead time
ST opens new SiC power device packaging line in Morocco
Previous
Texas Instruments announces new Bluetooth wireless MCUs, making high-quality RF and power performance more affordable
Next

All Comments (0)

Back
No Comment.

Top Post

Mouser Electronics expands to the Philippines with local customer service center
Fire broke out at AKM factory in Japan
Qualcomm ranked first in the world's top ten IC design companies
TSMC’s CoWoS capacity to reach 75,000 wafers/month by end-2025
Analyze the key factors and prospects of electronic components shortage from the perspective of wafer industry
onsemi expects to produce 200mm SiC wafers by 2025

Subscribe SemiMedia

Please check your E-mail to confirm the subscribtion.

Related posts

AMD taps GlobalFoundries for MI500 photonics as it advances CPO design

AMD taps GlobalFoundries for MI500 photonics as it advances CPO design

April 22, 2026
0
Microchip launches CLB MCUs to improve timing control and cut system cost

Microchip launches CLB MCUs to improve timing control and cut system cost

April 22, 2026
0
EU to launch Chips Act 2.0 in May to speed funding and boost local ecosystem

EU to launch Chips Act 2.0 in May to speed funding and boost local ecosystem

April 22, 2026
0
Samsung targets May samples for HBM4E, eyes Nvidia AI demand

Samsung targets May samples for HBM4E, eyes Nvidia AI demand

April 21, 2026
0
1
Copyright © 2017-2026 SemiMedia. Designed by nicetheme.
  • Please set up your first menu at [Admin -> Appearance -> Menus]
  • electronic components news
  • Electronic components supplier
  • Electronic parts supplier
  • Infineon
  • Electronic component news
  • Electronic components distributor
  • Renesas
  • Vishay
  • STMicroelectronics
  • NXP

SemiMediaEdit

Administrator