November 23, 2026 / SemiMedia / — Rapidus’s progress toward commercially viable 2nm yields is under scrutiny after reports that it missed a planned summer milestone for working SRAM. Tom’s Hardware, citing earlier reporting, said the Japanese foundry also faces cleanroom particle-control issues. Rapidus has not disclosed a numerical SRAM yield or confirmed a production delay.
The company announced electrical characterization of prototype 2nm gate-all-around transistors at its IIM-1 fab in Hokkaido in July 2025. That established an important device milestone. Demonstrating that a transistor operates, however, does not establish that large integrated circuits can be manufactured consistently at an acceptable yield.
SRAM arrays provide a more demanding test of process integration. A conventional six-transistor bitcell must balance devices closely enough to read, write and retain data reliably. Threshold-voltage variation can reduce those operating margins, while faults in contacts and interconnects can disable cells. Repeating the structure across a large array exposes variation and defects that isolated transistor measurements may miss.
The reports do not establish whether Rapidus’s difficulty concerns individual cells, larger arrays or electrical performance at the intended operating conditions. They also provide no sample count or pass-rate data. A specific yield of zero cannot be established from those disclosures.
For context, TSMC has published N2 research reporting yields above 90% on 256 Mb SRAM test vehicles, alongside reliability qualification results. Such figures describe the particular test structures and conditions, rather than the production yield of a complete processor. Rapidus has not published comparable SRAM array data.
Rapidus is also reportedly working to improve cleanroom dust and particle control. Contamination can create manufacturing defects, although the reports do not establish its contribution to the SRAM development difficulties.
Rapidus says it continues to target production in the second half of fiscal 2027, covering October 2027 through March 2028. The manufacturing challenge is to move from functional devices to repeatable SRAM arrays, then demonstrate reliable integrated circuits and stable yields across wafers and production lots. Delays in those steps would leave less time for customer qualification and the volume ramp.