Home › MarketWatch › Nikkei: Semiconductor equipment lead time extended again
  • 0

Nikkei: Semiconductor equipment lead time extended again

SemiMediaEdit
April 8, 2022

According to Nikkei Asia, the lead time for key semiconductor manufacturing equipment has been extended to a year and a half or more, as unprecedented parts shortages and tight supply chains have battered the semiconductor equipment industry.

The report mentioned that semiconductor equipment manufacturers such as Applied Materials, KLAC, Lam Research, and ASML have warned customers that some key machines must wait up to 18 months, because most parts are in short supply, including lenses, valves and pumps, microcontrollers , engineering plastics and electronic modules, etc.

At the same time, demand from chip makers has surged. TSMC, UMC, Intel and Samsung Electronics all plan to ramp up production, some of which will start as early as next year, and they are starting to worry that long equipment lead times will affect those plans.

The report pointed out that before the outbreak of Covid-19 in 2019, the average lead time of equipment was about 3 to 4 months, and in 2021, it was 10 to 12 months. According to industry sources, the current waiting time for KLAC testing equipment is more than 20 months. The chairman of Unimicron, the world's largest maker of chip substrates, said delivery of equipment used to make the substrates could take up to 30 months, compared with 12 to 18 months last year.

Related

electronic components news Semiconductor equipment sales
TDK releases new Y2 capacitors for high-temperature requirements
Previous
Knometa: Samsung ranked first in total global foundry capacity in 2021
Next

All Comments (0)

Back
No Comment.

Top Post

Mouser Electronics expands to the Philippines with local customer service center
Fire broke out at AKM factory in Japan
Qualcomm ranked first in the world's top ten IC design companies
TSMC’s CoWoS capacity to reach 75,000 wafers/month by end-2025
Analyze the key factors and prospects of electronic components shortage from the perspective of wafer industry
onsemi expects to produce 200mm SiC wafers by 2025

Subscribe SemiMedia

Please check your E-mail to confirm the subscribtion.

Related posts

KEMET to raise tantalum capacitor prices from April

KEMET to raise tantalum capacitor prices from April

March 3, 2026
0
WSTS: global chip market grew 25.6% in 2025 on AI demand

WSTS: global chip market grew 25.6% in 2025 on AI demand

March 3, 2026
0
Phison tightens payment terms amid rising NAND prices

Phison tightens payment terms amid rising NAND prices

March 3, 2026
0
Japan to invest 250 billion yen more in Rapidus to advance 2nm push

Japan to invest 250 billion yen more in Rapidus to advance 2nm push

March 2, 2026
0
Copyright © 2017-2026 SemiMedia. Designed by nicetheme.
  • Please set up your first menu at [Admin -> Appearance -> Menus]
  • electronic components news
  • Electronic components supplier
  • Electronic parts supplier
  • Infineon
  • Electronic component news
  • Renesas
  • Vishay
  • STMicroelectronics
  • NXP
  • TDK

SemiMediaEdit

Administrator